History
Diversifying into power
GSPC Group decided to move into power generation as a part of its corporate diversification plan and embarked on a short gestation power project based on the use of natural gas from its gas fields. The Hazira area of Gujarat was chosen as the site for its first combined cycle power plant. To implement the project, GSPC promoted a separate company named Gujarat State Energy Generation Ltd (GSEG).
GSEG, in turn, selected Alstom as contractor for the project through international competitive bidding. Alstom supplied the plant on a turnkey basis. Its scope included two GT8C2 gas turbines with generators, a steam turbine with generator and heat recovery steam generators as well as the overall power plant control system. The contract also included civil works, balance-of-plant and buildings. GSEG employed Desein Consulting Engineers of Delhi as advisors and to supervise the turnkey contractor's compliance with the plant specification.
GSEG selected Evonik Energy Services (India) Private Ltd erstwhile Steag Encotec as O&M contractor for the project. The power purchase agreement for the project was signed with GUVNL (erstwhile GEB).
Project Development Highlights
Germination
Gujarat State Petroleum Corporation Ltd. (GSPC), engaged in Oil & Gas E & P, decided to diversify into downstream activities for value addition in the energy business and thus, GSEG was incorporated in December 1998.

Contractual Structure of the Hazira project
Abbreviations: GSPC = Gujarat State Petroleum Corporation Ltd.; GSEG = Gujarat State Energy Generation Ltd;
GUVNL = Gujarat Urja Vikas Nigam Limited; INAP = Alstom Power India; CIF = Cost insurance, freight; Alstom Power Switzerland
Plan Project Schedule
| • |
OPEN CYCLE(GT1) in 17 months |
|
• |
OPEN CYCLE(GT2) in 18 months |
|
• |
COMBINED CYCLE in 20.6 months |
from the Notice to Proceed (NTP) to the EPC contract
Plan for a 156.1 MW, two 52 MW Gas Turbine (GT8C2), one 52.1 MW Steam Turbine and two Heat Recovery Steam Generator - Combined Cycle Power generation project takes shape.
Actualisation
Association with other state sector companies and central sector PSUs like KRIBHCO & GAIL
Alstom Power India awarded with EPC for the plant
The plants made available both as modularised, pre-engineered packages (for this low-gestation project)
Development for a 156.1 MW, two 52 MW Gas Turbine (GT8C2), one 52.1 MW Steam Turbine and two Heat Recovery Steam Generator-Combined Cycle
Power generation project begins at Surat
Put in place - electrical equipment, instrumentation and control system, and other necessary plant equipment as well as the HV switchyard
30th Sept, 2001. Successful initial test firing and synchronizing of the first Gas Turbine.
1st Dec, 2001. Plant operational in open cycle mode
"The Plant in Combined Cycle mode (156.1 MW) is commercially operational since 1st June 2002."